At Amangeldy gas field the works on construction of the first starting complex are almost finishing.
09.09.03 00:00
/Kazakhstan today, 09.09.03/ - At Amangeldy gas field the works on construction
of the first starting complex of the main technological line of the complex gas
processing equipment, consisting of 5 gas wells are approaching the end. The
president of Kazstroipromtechmontazh CJSC on southern region Shaismail
Gasanov informed about this fact the correspondent of KZ-today.
According to the information of S. Gasanov, at current Amangeldy - Taraz
pipeline (with the length of 193 km) is ready for exploitation. After
successful hydro experiments and refinement of the internal cavity, it is
filled with the gas of fifth compressor station of the bulk supply and was
preserved under pressure till its implementation. The gas supply in Taraz from
the gas field is planned to be started at the start of the heating season.
Besides, according to the director of Kazburgas OJSC branch Mailk Shotai, the
deepening of 3 out of 12 wells is being conducted, which is to be included into
the second starting complex of Amangeldy gas field. By the end of 2003 it is
planned to bore one more well.
As the head of the department of industry and energy of the Akimat Yerik
Kushebayev said, currently the assembling of technical equipment at central
facility is already finished, the binning of interplant communications and
assembling and setting up of control equipment is held.
The volume of the investments in developing of Amangeldy gas field comprised
$51 mln from republican budget, $67 mln from investments and $33 mln provided
by KazTransGas CJSC.
[2003-09-09]