KazTransOil plans to complete project "The first stage of the reverse section of the Kenkiyak-Atyrau oil pipeline" in 2021
05.01.21 16:29
/KASE, January 5, 2021/ – KazTransOil (Nur-Sultan), whose shares are officially
listed on Kazakhstan Stock Exchange (KASE), has provided KASE with the
following press release dated January 5, 2021:
quote
"KazTransOil" JSC will complete in 2021 the investment project "The first stage
of the reverse section of the Kenkiyak-Atyrau oil pipeline with a capacity of
up to 6 million tons per year". Originally, the project was planned to be
completed in 2020. The adjustment of the term was approved by JSC NC
"KazMunayGas" and is due to the impact of the COVID-19 pandemic.
All activities within the first launch complex of the project were completed in
June 2020. In particular, built a two-line jumper of the pipeline with a total
length of 6.5 km from the Head Oil Pumping Station named after N. Shmanov to
the oil pipeline "Atyrau-Kenkiyak" with areas of commercial oil metering
station site and start reception clearing device. Reconstruction of the
facilities of "MunaiTas" LLP on the territory of the Oil Pumping Station n.a.
T. Kasymov, OPS "Kenkiyak", and the linear part of the "Kenkiyak- Atyrau" oil
pipeline has been completed. Acceptance of the facilities of the first start-up
facilities made it possible to increase the volume of oil transportation in
reverse mode from 90-100 thousand to 190-200 thousand tons per month from July
1, 2020. As part of the second start-up facilities at the OPS Aman construction
site, hydraulic tests of process pipelines were carried out, and a tie-in was
made to the Kenkiyak-Atyrau oil trunk pipeline at the connection point of the
treatment unit launching unit at 226 km. All works, including commissioning,
have been completed at the OPS Kulsary and OPS Aman. In addition, voltage was
supplied to two high-voltage lines of 110 kV, a complete transformer substation
10/04 kV of the OPS Aman and the main pumping units of the OPS Aman.
The project "The first stage of the reverse section of the Kenkiyak-Atyrau oil
pipeline with a capacity of up to 6 million tons per year" is one of the stages
of construction and development of the "Kazakhstan-China" oil pipeline system.
Putting it into operation will allow for the transportation of oil from West
Kazakhstan fields in the reverse direction in the amount of up to 6 million tons
per year to Pavlodar and Shymkent refineries, as well as for export to China
via the "Atasu-Alashankou" oil pipeline and railway tanks using "Shagyr"
loading station.
unquote
[2021-01-05]