KazTransOil plans to complete project "The first stage of the reverse section of the Kenkiyak-Atyrau oil pipeline" in 2021

05.01.21 16:29
/KASE, January 5, 2021/ – KazTransOil (Nur-Sultan), whose shares are officially listed on Kazakhstan Stock Exchange (KASE), has provided KASE with the following press release dated January 5, 2021: quote "KazTransOil" JSC will complete in 2021 the investment project "The first stage of the reverse section of the Kenkiyak-Atyrau oil pipeline with a capacity of up to 6 million tons per year". Originally, the project was planned to be completed in 2020. The adjustment of the term was approved by JSC NC "KazMunayGas" and is due to the impact of the COVID-19 pandemic. All activities within the first launch complex of the project were completed in June 2020. In particular, built a two-line jumper of the pipeline with a total length of 6.5 km from the Head Oil Pumping Station named after N. Shmanov to the oil pipeline "Atyrau-Kenkiyak" with areas of commercial oil metering station site and start reception clearing device. Reconstruction of the facilities of "MunaiTas" LLP on the territory of the Oil Pumping Station n.a. T. Kasymov, OPS "Kenkiyak", and the linear part of the "Kenkiyak- Atyrau" oil pipeline has been completed. Acceptance of the facilities of the first start-up facilities made it possible to increase the volume of oil transportation in reverse mode from 90-100 thousand to 190-200 thousand tons per month from July 1, 2020. As part of the second start-up facilities at the OPS Aman construction site, hydraulic tests of process pipelines were carried out, and a tie-in was made to the Kenkiyak-Atyrau oil trunk pipeline at the connection point of the treatment unit launching unit at 226 km. All works, including commissioning, have been completed at the OPS Kulsary and OPS Aman. In addition, voltage was supplied to two high-voltage lines of 110 kV, a complete transformer substation 10/04 kV of the OPS Aman and the main pumping units of the OPS Aman. The project "The first stage of the reverse section of the Kenkiyak-Atyrau oil pipeline with a capacity of up to 6 million tons per year" is one of the stages of construction and development of the "Kazakhstan-China" oil pipeline system. Putting it into operation will allow for the transportation of oil from West Kazakhstan fields in the reverse direction in the amount of up to 6 million tons per year to Pavlodar and Shymkent refineries, as well as for export to China via the "Atasu-Alashankou" oil pipeline and railway tanks using "Shagyr" loading station. unquote [2021-01-05]