Pipelines exploitation department of KazTransOil CJSC informs about performed works in first six months of 2001
18.07.01 00:00
/IRBIS, July 18, 01/ - According to pipelines exploitation department of
KazTransOil CJSC (Astana) company realized work aimed at diagnostic of
line part of pipeline, pipeline and tanks technology, current equipment
repairing works, relay protection. Diagnostically work at Kenkiyak - ORSK,
Priirtishsk - Pavlodar were completed for today.
Examination works for waterways, ecological monitoring over ground water
and atmosphere, elaboration of projects for admitted contamination (AC) at
presence of PED.
Specialists of PED declared 35 tenders for these programs realization. PED
budgeted 98% in first six months. The basic accent on budget
implementation will be in third quarter of this year. By the results of tenders
agreements have been concluded with subcontractors. Today KazTransOil
CJSC works at isolation o technical pipelines, diagnostically examination of
tanks. By the condition for July 1, 2001 26 reservoirs were examined and
total at KZT16m from the budget planned KZT24.5m.
According to the information KazTransOil completely implemented
semiannual program aimed at heating isolation of technical pipelines.
Equipment mobilization and delivery works have been started. Aircontrol of
pipelines is being held. Ventilation systems of Western and Aktubinsk
branches were checked. Fire protection works of wooden constructions are
being held.
KazTransOil CJSC public relations department informs that company settled
over KZT34m during first six months of 2001 to provide with technical safety
and security. According to concluded contracts recultivation of earth and oil
waste remove is regularly being held.