SevKazEnergo (Kazakhstan) informs of First deputy prime-minister of Republic of Kazakhstan S. Akhmetov visiting Petropavlovsk TEC-2
26.04.12 11:02
/KASE, April 26, 12/ - JSC "SevKazEnergo" (Petropavlovsk), whose bonds are
officially listed at Kazakhstan Stock Exchange (KASE), has provided KASE with
the following press-release:
quote
On April 20, 2012 First deputy prime-minister of Republic of Kazakhstan
Serik Akhmetov paid a visit to Petropavlovsk TEC-2 in the course of his
business trip to North-Kazakhstan region
Visiting of Petropavlovsk TEC-2 was one of items in the program of visits of
regional industrial and agricultural enterprises performed by First deputy prime-
minister of Republic of Kazakhstan Serik Akhmetov. In the course of the visit
Chairman of the Board of Directors of JSC "SEVKAZENERGO" Erkin
Amirkhanov briefed the Prime-minister on the progress of the Company's
investment programme scheduled for 2010-2015. It was pointed out that the
company was planning to install three new turbines and one boiler unit at the
station and complete a full reconstruction of four boiler units by 2015.
In the course of the visit S. Akhmetov was shown the operation of modernized
boiler unit No. 6 launched after a reconstruction in January 2012. After the full
replacement of the heating surface, changing of the burning mode and
installation of the ash-catching equipment, the steam output was increased from
220 to 270 tons of steam an hour. First prime-minister also inquired about the
progress of installation of new boiler unit No. 8 manufactured at OJSC
"Sibenergomash" (Barnaul, Russia), whose launch is scheduled for the second
half-year of 2013. The cost of boiler unit No. 8 made up KZT1,790 bn, the overall
cost of the project - KZT4,6 bn. Also the guests were briefed on the progress of
modernization of boiler unit No. 7 supposed to be completed by the end of this
year.
As a result of "SEVKAZENERGO"'s investment program in accordance with the
"Margin tariffs" it is expected the depreciation of the equipment will reduce from
the current 70-75% to 40-45% by 2016.
"After completing the entire modernization program, the quantity of boiler units
will reach 12, instead of 11 currently operating, and the specified capacity of
the station will go up by 78 MWt, from 357 MWt to 435 MWt. As a result of this
program's implementation, the obsolete equipment will be upgraded to 35-40%
by 2016", - pointed out Erkin Amirkhanov.
Projects being implemented at Petropavlovsk TEC-2 are another evidence of a
fair fulfillment of investment obligations of "SEVKAZENERGO" towards the
Ministry of Industry and New Technologies of the Republic of Kazakhstan
regarding modernization and upgrading of equipment, fixed assets, and
improvement of environmental situation in the Company's operating zone.
JSC "SEVKAZENERGO" is part of the integrated power holding JSC "Central
Asian Power Energy Corporation", which is the largest private electricity
company in Kazakhstan. Under the corporation's umbrella there are energy
enterprises which generate, transport, and market electricity and heat energy in
Pavlodar region and North-Kazakhstan region, and also perform marketing in
Astana.
Press-service of JSC "SEVKAZENERGO"
Tel +7(7152) 41-29-39
Email PR@SK-energo.kz
ae-glredpr@sk-energo.kz
www.sevkazenergo.kz
unquote