From TCO recovered KZT204.0 million for environmental pollution
22.07.10 16:06
/IRBIS, July 22, 2010/ - At the proposal of the environmental prosecutor in the
Atyrau region LLP TCO for allowing the excess regulatory pollution recovered
204,032 821tenge, stated in a July 21 press service of the Prosecutor Atyrau
region.
As indicated, May 19, 2010 at 13:30 pm due to the higher-level separators F-
205, on the CPL-1, CPL-2 stopped all Compressor GC-201. During the stop of
compressors for CPL-1, 2 through the valves 2X PIC-008 were produced
dumping of acid gas on a torch to burn, resulting in environmental damage.
The violation of ecological requirements of the LLP TCO Atyrau oblast
environmental prosecutor's office for appropriate action had been made in the
presentation of the Ural-Caspian Department of Ecology.
"After reviewing the submission of the authorized body had imposed an
administrative fine of article 243 of the Administrative Code of Kazakhstan in
the amount of 17,897,026 m. In addition, a claim for damages caused to the
environment in the amount of KZT186,135,795", - stated in the message.
Thus, as a result of measures taken Prosecutorial TCO in July 2010 in state
income fully paid fines and reparation to the total amount of KZT204,032,821.
[2010-07-22]