/RESTATED/ NGSK KazStroyService (Kazakhstan) finishes construction of line part of pipeline Kenkiyak-Kumkol
02.07.09 12:44
/KASE, July 2, 09, resent due to editorial amendments of the text by NGSK
KazStroyService/ - NGSK KazStroyService (Almaty), a company listed on
Kazakhstan Stock Exchange (KASE), provided KASE with a press release:
Quotation beginning
The first oil for starting works is planned in the nearest time by
representatives of Customer Kazakhstansko-Kitayskiy truboprovod, General
Subcontractor NGSK KazStroyService and Oil pumping operator KazTransOil.
A General SUBCONTRACTOR of the project for construction of oil pipeline
KENKIYAK-KUMKOL, HGSK KazstroyService designed, supplied equipment and
constructed 3 sites turnkey:
- oil pipeline length is 483.2 km, diameter 813 mm;
- with 21 block value stations;
- 3 pig launching and receiving units.
Over 2,500 employees of HGSK KazStroyService and subcontract organizations
worked to launch the project. The company gave over 200 jobs to specialists from
Aktobe and Kzylorda oblasts. Local workers had an opportunity to complete
special training to operate newest automatic welding equipment, which allowed
for receiving an expertise in largest international projects.
Today HGSK KazStroyService is launching the second part of an international
branch line. The total length of oil pipeline KENKIYAK-KUMKOL is 793 km, with
pipe diameter 813 mm. Capacity at the initial stage is 10 m tonnes oil a year
with further increase up to 20 m tonnes oil a year. The resource bases of the
project are deposits of Aktobe oblast and Western Kazakhstan.
The full scale construction of the pipeline began in 2008. It was planned to
finish the construction in August 2009. However, HGSK KazStroyService completed
the works ahead of schedule. A working commission composed of the Customer
Kazakhstansko-Kitayskiy truboprovod and other monitoring agencies visited the
site on June 23, 2009 and acknowledged the works of the General subcontractor
satisfactory.
The project will affect the entire oil and gas sector opening new opportunities
to sell Kazakhstan oil. The project will have a significant economical effect -
according to the forecast of National Company KazMunaiGas, section
KENKIYAK-KUMKOL in the period 2010 through 2020 will bring Kazakhstan
KZT60 bn tax payments.
This is not the first international project of NGSK KazStroyService. In July
2006 the company built and commissioned the first part of oil pipeline
Kazakhstan- China, section ATASU-ALASHANKOU. Moreover, NGSK KazStroyService is a
General subcontractor of construction of gas pipeline Kazakhstan-China. The
company has sufficient resources and expertise to implement entrusted projects.
Contact:
Zhanna Utarbaeva, Public Relations KazStroyService:
Tel/fax: +7 (727) 258 14 42
Cell: +7 701 999 40 03
e-mail: zhanna.utarbayeva@kazstroyservice.kz
web-site: www.kazstroyservice.kz
Quotation end
[2009-07-02]